We are pleased to report that work is set to begin on the Heath Crescent stairs and slope project in early 2027. What began more than a decade ago as a simple request to replace damaged sections of a staircase has evolved into a significant, multi-faceted project which will unfurl over an extended period of time. The activity will be disruptive, but we strongly believe the outcome will be net‑positive for ravine health, neighbourhood connectivity, and safer recreation.
The expanded project stems from Toronto and Region Conservation Authority (TRCA) studies that identified serious slope instability driven by increasingly intense stormwater flows through Yellow Creek, which drains roughly 10 sq. km to the north. The gabion baskets intended for erosion control are failing and the creek banks are collapsing. Rehabilitation is needed to both stabilize the ravine slope and to provide a secure base for the new stairs.
The project will require construction of a temporary access road through the ravine to accommodate heavy equipment. Trail closures will be necessary to keep users away from heavy equipment, active work areas, and unstable ground. The scope of these closures has not yet been finalized. Some trees will need to be removed along the access road and work site. We understand that it is TRCA’s intention to minimize the impact of the project on significant trees, habitats, and use of ravine trails.
Upon completion of construction, the TRCA will replant the area with trees and shrubs. Project completion is anticipated for the summer of 2028.
We would be remiss not to thank both Councillor Matlow and former Councillor Saxe for their meaningful support to get this project underway.
More information
The program for the overall rehabilitation of the Vale of Avoca is continuing to take shape. While we will keep you updated, the City has created a Vale of Avoca project page where you can follow along. You can also sign up for updates under the “Get Involved” section.